For those companies owning generation on the Bonneville Power Administration system, mark your calendars for March 15, 2014.  That’s the day by which you must submit your facility displacement costs for Bonneville’s implementation of its Oversupply Management Protocol (aka Environmental Redispatch) that provides compensation for certain generator curtailments.  The failure to submit facility displacement costs will result in a displacement cost of $0.00 per MWh.  

So begin registering your facility with Bonneville now at https://oversupply.accionpower.com so that you are prepared for when Bonneville begins accepting displacement cost information on February 28.