After the years of inconclusive resource planning, months of contested case proceedings, and days of oral argument, discussion and review that led to today’s deliberations, the Minnesota Public Utilities Commission (“Commission”) unanimously decided not to decide. The ultimate question before the Commission was what capacity needs had been determined in the record and what should

At the close of last year, Minnesota Administrative Law Judge Eric Lipman determined that the single solar proposal in a competitive resource acquisition process would provide the best value to Xcel ratepayers (see more here). Key to his decision was his conclusion that Xcel’s capacity needs in the timeframe considered were uncertain and potentially