Minnesota PUC Settles Longstanding Dispute over REC Ownership
Last week, the Minnesota Public Utilities Commission resolved a longstanding dispute over who owns Renewable Energy Credits (RECs) when the Power Purchase Agreement (PPA) is silent. Following the establishment of an REC tracking system for Minnesota, Xcel Energy asked the Commission to clarify ownership of RECs associated with 46 wind, biomass, hydro, and landfill gas facilities totaling 467.5 MW. These PPAs were written before the concept of RECs existed.
On August 17, 2010, the Commission resolved the dispute partially in favor of Xcel and partially in favor of the generators. The Commission divided the disputed PPAs into two categories: 1) PPAs signed under 1978 federal Public Utilities Regulatory Policy Act (PURPA) and 2) PPAs signed under Minnesota’s 1994 wind and biomass mandates (Minn. Stat. §§216B.2423 and 216B.2424).
For the PURPA contracts, the Commission decided that the generators are the rightful owners of RECs because they had only been paid avoided cost with no premium for the electricity being from renewable sources.
For the wind and biomass mandate PPAs, the Commission favored Xcel and decided that the utility had acquired ownership of the RECs, unless the generator can make a showing that the PPA is not silent on REC ownership. For this category, the Commission reasoned that Xcel had contracted to buy electricity that would meet specific renewable mandates. Without the RECs, the electricity would not satisfy the renewable mandates.
The Commission exempted two PPAs close to being privately settled from its decision as well as 13 PPAs that were already privately settled.
Filings related to the "silent PPAs" dispute can be found by searching for Docket No. E-002/08-440 in Minnesota’s eDocket system.
XCEL Plans New Wind Solicitation In Connection With Anson Plant
In a January 8 letter to the Minnesota Public Service Commission, Xcel Energy informed the Commission that it intends to conduct competitive negotiations with wind projects that are able to interconnect at Xcel's Angus Anson generating station in Sioux Falls.
The Angus Anson plant is a gas-fired peaking facility that has firm transmission to deliver its output. Xcel wants to make better use of this transmission by looking at ways to locate wind generating capacity nearby and connect it to the transmission system at Anson. Over the next several months, Xcel plans to accept proposals and conduct competitive negotiations for wind projects that can interconnect at the Anson site. Xcel does not believe that transmission upgrades will be needed for the proposed interconnection.
Minnesota Renewable Energy Projects RFP
The State of Minnesota’s Office of Energy Security (OES) is requesting proposals from organizations that are engaged in or will engage in the manufacture of renewable energy systems or fuels, energy storage systems, geothermal energy systems for heating and cooling, components of these systems, or equipment for the manufacture of these systems or components.
The maximum award is $1 million. Up to a total of $2 million is available to all recipients. OES anticipates that two to six projects will be selected for awards under this solicitation.
All work to be performed within a proposed scope of work must be completed no later than June 30, 2011. An applicant must provide at least 40 percent of the total cost of the proposed scope of work. Applicant’s match may be cash or in-kind.
Each applicant must submit a notice of intent no later than December 4, 2009 to be eligible. Final proposals are due on December 18, 2009. OES anticipates provisional notification of successful applicants no later than January 29, 2010. Final selection will be contingent on determination by U.S. Department of Energy of compliance with the National Environmental Policy Act.
For more information and to download a copy of the RFP, please visit www.energy.mn.gov and click on Active Request for Proposal (RFP).
The Wind Energy Promotion Act: Turbo Charging the Renewable Energy Production Tax Credit
U.S. Representatives Collin Peterson (MN) and Tim Walz (MN) introduced the Wind Energy Promotion Act (WEPA) last month. If WEPA becomes federal law, the Renewable Energy Production Tax Credit (PTC) promises to become an even more potent driver for wind power project development. Under current law, the PTC may only be used to shelter passive activity income from tax liability.
If adopted, WEPA would allow the use of the PTC to shelter up to $40,000 of ordinary income, a modification that would boost the effectiveness of the PTC.
Click here to read the full analysis on WEPA and the opportunities this presents.
For more information, please contact Joel Dahlgren of our Minneapolis office, or any of our other energy attorneys.
Minnesota Think Tank Estimates 4,000 MW of More Wind Power Needed
In a recent report published by Minnesota 2020, a non-partisan think tank focused on public policy matters including economic development, health care, education and transportation, the group notes that Minnesota needs an additional 4,000 MW of wind power to meet its Renewable Energy Standard, set at 25% by 2025. The think tank also notes that achieving the RES would "create up to 2,200 new jobs during the 17-year construction phase and more than 900 sustained jobs during the wind farms lifetime operations," which numbers may increase as Minnesota reaches beyond its minimum 25% requirement. The report also includes several short- and long-term recommendations to encourage the presence of wind energy companies in Minnesota, and thus the market (including training) for jobs within the wind industry as well.
New Minnesota Solar Power Incentives
Minnesota politicians held a news conference yesterday on the state capitol mall to provide an overview of recent legislation relating to solar energy projects. Minnesota has allocated $14.5 million in stimulus money for renewable energy projects, with a portion flagged for solar projects to encourage the installation and use of solar-powered systems. Another piece of legislation gives utilities the opportunity to double their commitments to solar energy projects under the Conservation Improvement Program currently in place. Representatives from Xcel Energy Inc. (Xcel), which serves more than 1.2 million customers in Minnesota, announced yesterday that they filed a $280 million plan with regulators to offer incentives for Minnesota customers to conserve energy, which could include installation of solar panels on homes and businesses. Under Xcel’s proposed “Solar Rewards Program,” Xcel would provide rebates to customers who install solar photovoltaic systems of up to 40 kilowatts on their premises.
Deadline Approaching for Minnesota Biodiesel Grants
The Minnesota Department of Agriculture has announced that it will be providing $300,000 in grants to qualified applicants to use for the addition of infrastructure that would allow for the blending of biodiesel in all types of weather, including cold conditions. Facilities must offer biodiesel for a minimum of five years, contingent upon the availability of diesel or biodiesel fuel. The Grantee must notify the Minnesota Department of Agriculture in writing in the event that diesel or biodiesel fuel is not readily available. Complete information is available on the Department's website.
The deadline for submitting applications is December 12, 2008.