At the July 27, 2023, Open Meeting, the Federal Energy Regulatory Commission (FERC) issued long-awaited Order No. 2023, the Final Rule on Improvements to Generator Interconnection Procedures and Agreements in Docket No. RM22-14-000.  The rulemaking arose from the Advanced Notice of Proposed Rulemaking: Building for the Future Through Electric Regional Transmission Planning and Cost

Yesterday, February 14, 2023, the D.C. Circuit issued an order affirming FERC’s order in Broadview Solar, LLC, 174 FERC 61,199 (2021) and its “send-out” approach to determining the net power production capacity of a Qualifying Facility (“QF”).  As a brief recap of the history of Broadview, Broadview filed an application for QF certification

At its June 16, 2022, open meeting, the Federal Energy Regulatory Commission (FERC or Commission) issued a notice of proposed rulemaking (NOPR), Improvements to Generator Interconnection Procedures and Agreements, 179 FERC ¶ 61,194 (2022), proposing reforms to the Commission’s standard generator interconnection procedures and agreements.  The goal of the NOPR is to reduce queue

On November 18, 2021, FERC issued a Notice of Inquiry (NOI) seeking comments on reactive power capability compensation and market design.  (Link to NOI here). Reactive power is a critical component of the bulk electric system. Almost all bulk electric power is generated, transported, and consumed in AC networks. These AC systems consume both real and reactive power. Reactive power supports the voltages necessary for system reliability to allow the supply of real power from generation to load. All balancing authorities must procure enough sources of reactive power to safely manage the grid and generator interconnection agreements contain provisions requiring generators to operate within certain reactive power limits. Reactive power is an ancillary service and costs are recovered separately from the cost of standard transmission service.
Continue Reading Reactive Power Compensation for Renewable Generators – On the Chopping Block?

In the wake of Governor Newsom’s July 30, 2021 Emergency Proclamation intended to mitigate the strain on the California energy grid, the California Department of Water Resources (CDWR) and the California Energy Commission have been reaching out to generation owners that could accommodate the addition of 30 MW gas turbines generators, an effort now referred to as the State Power Augmentation Project.  So far, two sites have been found:  Greenleaf 1 in Yuba City and Roseville Energy Park.  Each site will accommodate two turbines.  The units were supposed to come online in mid-September.

The two turbines at Roseville Energy Park will be interconnected through the Balancing Authority of Northern California and will participate in the California ISO’s (CAISO) energy imbalance market.  The two turbines at Greenleaf 1 will interconnect to the CAISO.  Under current tariff provisions, the CAISO can interconnect 50 MWs of the 60 MW total.  The Greenleaf 1 site has cogeneration facilities that are currently mothballed but still retain existing interconnection capacity of 49.2 MWs.  Because both the cogeneration facilities and the new gas turbines are gas-fired, there will be no change to the electrical characteristics, and the CAISO can therefore interconnect the two turbines under the repowering provisions of the tariff, but only up to 49.2 MWs.
Continue Reading FERC Grants Limited Waiver to the CAISO to Immediately Interconnect Gas Turbines

Today was a big day for the solar power industry at the Federal Energy Regulatory Commission (FERC).

In its monthly open meeting, FERC announced two decisions that significantly impact the industry — one involving PURPA and the other related to PJM’s Minimum Offer Price Rule (MOPR).

First, FERC reversed its Broadview Solar decision issued in

Yesterday, the Federal Energy Regulatory Commission (FERC) issued Order No. 872 and implemented the largest overhaul to FERC’s regulations affecting Qualifying Facilities (QFs) in more than a decade.  The order itself is 491 pages in length and there remain plenty of details to unpack in its implementation (including future proceedings to come at the FERC

On Friday, July 10, 2020, the U.S. Court of Appeals for the D.C. Circuit (“D.C. Circuit”) upheld the Federal Energy Regulatory Commission’s (“FERC”) Order Nos. 841 and 841A, which established a framework for electric storage resources’ (“ESRs”) participation in wholesale markets. The D.C. Circuit rejected the petitioners’ arguments that FERC exceeded its jurisdictional boundaries and

On June 30, the DC Circuit struck down the Federal Energy Regulatory Commission’s (FERC) use of tolling orders to buy additional time in responding to requests for rehearing—a longstanding agency practice that had the effect of materially delaying litigants’ rights to seek judicial review of FERC’s orders.  The opinion was issued in a case that