Yesterday, the Federal Energy Regulatory Commission (FERC) issued Order No. 872 and implemented the largest overhaul to FERC’s regulations affecting Qualifying Facilities (QFs) in more than a decade.  The order itself is 491 pages in length and there remain plenty of details to unpack in its implementation (including future proceedings to come at the FERC and state public utility commission level), but what is clear is that Order No. 872 substantially changes the ground rules for developing QFs.

Order No. 872 includes the following significant changes, among others:

  • One-Mile Rule.  There is no longer an irrebuttable presumption that projects located more than one mile from each other are considered to be at separate sites for purposes of qualification as a QF.  Rather, only projects located 10 miles from each other will benefit from an irrebuttable presumption, while projects that are between one and ten miles from each other will only be afforded a rebuttable presumption.  Furthermore, for purposes of determining whether QFs are located at the “same site,” FERC will consider several new factors including, but not limited to, shared transformers or generation interconnection facilities, common debt and equity financing, and common permitting and access rights.  None of these factors, which fall into the categories of physical characteristics or ownership/other characteristics, is dispositive in determining whether QFs are located at the “same site”; rather, FERC will weigh the evidence on a case-by-case basis.
  • Legally-Enforceable Obligations.  For QFs, establishing a legally-enforceable obligation, or a LEO, represents that point in time when power purchase agreement pricing is locked in.  Order No. 872 introduces new LEO regulations that require QFs to demonstrate commercial viability and a financial commitment to developing the project.  FERC left it for each state to determine how a LEO is formed there, but it suggested that a QF be required to demonstrate that it has completed, or at least undertaken, site control for the project, filed an interconnection application, and applied for the required permitting and zoning.  But ultimately FERC left it to each state agency to determine criteria for establishing a QF’s commercial viability and financial commitment.
  • Challenges to QF Status.  Prior to Order No. 872, a party challenging the QF status of a project was required to seek a declaratory order from FERC, which carries a roughly $30,000 price tag.  As the result of this order, parties challenging a QF’s status, including same site presumptions (which can be done after the filing of an initial QF self-certification or recertifications that make substantive changes) need not pursue a declaratory order and therefore will avoid the associated fee. Substantive changes in the QF recertification include changes in electrical generating equipment that increases power production capacity by the greater of 1 MW or 5% or a change in ownership in which an owner increases its equity interest by at least 10%. Thus, a change in upstream ownership of an existing QF may open up that QF to challenges regarding aggregation with other affiliated same fuel source facilities within 10 miles.
  • Avoided-Cost Rates.  Once again, FERC left it for the states to determine the proper method for determining a utility’s avoided costs.  Yesterday’s order allows state agencies to eliminate fixed avoided-cost energy rates (while still retaining fixed capacity rates) and to have instead the energy rates vary with changes in the utility’s as-available avoided costs as the energy is delivered. And if the state decides to retain fixed energy rates, the fixed energy rate can now be based on project energy prices at the anticipated time of delivery. There is a new rebuttable presumption that as-available energy rates can be based on locational marginal prices, if a utility is located within an organized market, or according to liquid trading hub prices or natural gas indices for those outside of organized markets.  Avoided costs may also be determined through a competitive solicitation (provided that it satisfies certain transparency and non-discriminatory procedures).  Thus, states will now decide if QFs will bear merchant risk in their power sales arrangements.
  • Must-Purchase Opt Out. Lastly, for several years, utilities have been able to opt out of their obligation to purchase from QFs that are larger than 20 MW and located within an organized market.  Yesterday’s order drops that threshold to 5 MW, meaning that utilities located within organized markets may apply to FERC for relief from the obligation to purchase power from QFs larger than 5 MW.

There is no avoiding the fact that Order No. 872 is a game-changer for QFs and utilities alike when it comes to PURPA, and yesterday’s order represents yet another instance where PURPA has become increasingly narrowed by FERC.  There is more to play out with respect to Order No. 872 and we will provide further details as its implementation signals the order’s true scope.

 

Print:
Email this postTweet this postLike this postShare this post on LinkedIn
Photo of Jessica Bayles Jessica Bayles

Jessica Bayles is a partner in Stoel Rives’ Energy Development group, where she focuses her practice on energy regulatory support for renewable project development and transactions, compliance counseling, and regulatory controversies. Jessica counsels renewable energy developers and asset managers on compliance with the…

Jessica Bayles is a partner in Stoel Rives’ Energy Development group, where she focuses her practice on energy regulatory support for renewable project development and transactions, compliance counseling, and regulatory controversies. Jessica counsels renewable energy developers and asset managers on compliance with the requirements of the Federal Energy Regulatory Commission (FERC). She has significant experience in complex litigation and settlement proceedings before FERC. She also advises large electric customers in state public utility commission proceedings.

Click here for Jessica Bayles’ full bio.

Photo of Jason Johns Jason Johns

Jason Johns advises independent power producers, utilities, investors, and large users of gas and power resources with matters arising in power markets and state and federal energy regulatory arenas. Jason appears regularly in proceedings before the Federal Energy Regulatory Commission and in negotiations…

Jason Johns advises independent power producers, utilities, investors, and large users of gas and power resources with matters arising in power markets and state and federal energy regulatory arenas. Jason appears regularly in proceedings before the Federal Energy Regulatory Commission and in negotiations at the ISO/RTO level, where he represents independent power developers and utilities. His experience includes negotiating major facility contracts, such as interconnection, transmission, and power purchase agreements; prosecuting disputes at FERC; and counseling and defending clients on issues related to regulatory compliance.

Jason also works closely with large commercial and industrial users of electricity and gas, such as aerospace companies, pulp and paper mills, steel mills, and tech company data centers. In that role, Jason helps clients negotiate power and gas supply contracts, interstate pipeline capacity asset management agreements, and pipeline bypass agreements. Jason has also assisted these clients with demand management agreements, the installation of on-site resources (such as battery storage, fuel cells, and solar PV), and with retail and wholesale power purchase agreements for renewable energy and other resources. Jason also serves as a board member of The Climate Trust, a national leader in carbon offset projects and innovative climate change solutions.

Jason and his wife are parents to two growing boys, and they live just outside of Portland, Oregon.

Click here for Jason John’s full bio.

Photo of Jennifer Mersing Jennifer Mersing

Jennifer Mersing, an attorney in Stoel Rives’ Energy & Regulatory group, focuses her practice on electric regulatory issues including Federal Energy Regulatory Commission (FERC) and certain state law matters. She advises electric utilities, transmission providers, large industrial consumers of power and energy…

Jennifer Mersing, an attorney in Stoel Rives’ Energy & Regulatory group, focuses her practice on electric regulatory issues including Federal Energy Regulatory Commission (FERC) and certain state law matters. She advises electric utilities, transmission providers, large industrial consumers of power and energy marketers regarding issues under the US Federal Power Act (FPA), the Public Utility Regulatory Policies Act of 1978 (PURPA), and the Public Utility Holding Company Act (PUHCA).