On September 6, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued an order finding that the presence of a non-independent director, i.e., one who is affiliated with an investor, on the board of directors of a public utility or its upstream holding company creates an affiliation between the sponsor and the investor
FERC
CAISO Interconnection Process Enhancements Proposal Faces Protest at FERC
CAISO’s Interconnection Process Enhancements proposal faces protests from independent power producers, clean energy organizations, and renewable energy developers at FERC. Challengers claim that CAISO’s scoring criteria provide undue influence to load-serving entities (LSEs) and may violate principles of open access.
CAISO’s proposal addresses the backlog in its interconnection queue by prioritizing projects in zones with…
Federal Energy Regulatory Commission Issues Long-Awaited Transmission Planning and Cost Allocation Final Rule
On May 13, 2024, at a special transmission reform meeting, the Federal Energy Regulatory Commission (FERC or Commission) issued Order No. 1920 “Building for the Future Through Electric Regional Transmission Planning and Cost Allocation” (Final Rule).[1] The Final Rule builds upon Order No. 888, Order No. 890, and Order No. 1000, which developed…
CAISO Releases Interconnection Process Enhancements Final Proposal
Summary
On March 29, 2024, the California Independent System Operator (CAISO) released the Track 2 final proposal for its Interconnection Process Enhancements (IPE) initiative. The proposed changes in the IPE proposal aim to address the “unprecedented and unsustainable interconnection request volumes” in the CAISO. CAISO proposes to adopt a zonal approach that prioritizes project interconnection in areas with existing or planned transmission capacity, to cap the number of projects permitted to proceed into the study process at 150% of the available and planned transmission capacity in specific zones, and adopt scoring criteria for eligibility and prioritization in the interconnection study process. Continue Reading CAISO Releases Interconnection Process Enhancements Final Proposal
FERC issues Final Rule on Improvements to Generator Interconnection Procedures and Agreements
At the July 27, 2023, Open Meeting, the Federal Energy Regulatory Commission (FERC) issued long-awaited Order No. 2023, the Final Rule on Improvements to Generator Interconnection Procedures and Agreements in Docket No. RM22-14-000. The rulemaking arose from the Advanced Notice of Proposed Rulemaking: Building for the Future Through Electric Regional Transmission Planning and Cost…
D.C. Circuit Affirms FERC’s Broadview Order Confirming that Qualifying Facilities May Install Greater than 80 MW of Nameplate Generating Capacity
7/8/2024 Update: The U.S. Supreme Court has vacated the D.C. Circuit’s order, discussed below. The D.C. Circuit applied Chevron deference in affirming FERC’s decision in the proceeding below. As a result, the U.S. Supreme Court has vacated and remanded back to the D.C. Circuit to reconsider the case in light of Chevron being overturned.
———–…
FERC Proposes Broad Reforms to Interconnection Process
At its June 16, 2022, open meeting, the Federal Energy Regulatory Commission (FERC or Commission) issued a notice of proposed rulemaking (NOPR), Improvements to Generator Interconnection Procedures and Agreements, 179 FERC ¶ 61,194 (2022), proposing reforms to the Commission’s standard generator interconnection procedures and agreements. The goal of the NOPR is to reduce queue…
Updated FERC Guidance on Qualifying Facility Certifications
FERC issued two notable orders this spring in Irradiant Partners, LP (Docket No. EL22-8-000) and Dalreed Solar (Docket No. QF20-1037-002) that provide further guidance on qualifying facility (QF) certifications. Here are the key takeaways:
- QF Re-Certifications Should Be Filed Before or At the Time of a Material Change: FERC’s regulations do not contain specific
…
Reactive Power Compensation for Renewable Generators – On the Chopping Block?
On November 18, 2021, FERC issued a Notice of Inquiry (NOI) seeking comments on reactive power capability compensation and market design. (Link to NOI here). Reactive power is a critical component of the bulk electric system. Almost all bulk electric power is generated, transported, and consumed in AC networks. These AC systems consume both real and reactive power. Reactive power supports the voltages necessary for system reliability to allow the supply of real power from generation to load. All balancing authorities must procure enough sources of reactive power to safely manage the grid and generator interconnection agreements contain provisions requiring generators to operate within certain reactive power limits. Reactive power is an ancillary service and costs are recovered separately from the cost of standard transmission service.
Continue Reading Reactive Power Compensation for Renewable Generators – On the Chopping Block?
FERC Grants Limited Waiver to the CAISO to Immediately Interconnect Gas Turbines
In the wake of Governor Newsom’s July 30, 2021 Emergency Proclamation intended to mitigate the strain on the California energy grid, the California Department of Water Resources (CDWR) and the California Energy Commission have been reaching out to generation owners that could accommodate the addition of 30 MW gas turbines generators, an effort now referred to as the State Power Augmentation Project. So far, two sites have been found: Greenleaf 1 in Yuba City and Roseville Energy Park. Each site will accommodate two turbines. The units were supposed to come online in mid-September.
The two turbines at Roseville Energy Park will be interconnected through the Balancing Authority of Northern California and will participate in the California ISO’s (CAISO) energy imbalance market. The two turbines at Greenleaf 1 will interconnect to the CAISO. Under current tariff provisions, the CAISO can interconnect 50 MWs of the 60 MW total. The Greenleaf 1 site has cogeneration facilities that are currently mothballed but still retain existing interconnection capacity of 49.2 MWs. Because both the cogeneration facilities and the new gas turbines are gas-fired, there will be no change to the electrical characteristics, and the CAISO can therefore interconnect the two turbines under the repowering provisions of the tariff, but only up to 49.2 MWs.
Continue Reading FERC Grants Limited Waiver to the CAISO to Immediately Interconnect Gas Turbines