The Federal Energy Regulatory Commission’s (“FERC”) long-awaited Order 845 (Reform of Generator Interconnection Procedures and Agreements) was issued on April 19 after over two years of consideration of the issues. Order 845 is the first grid-wide major reform of FERC’s Generator Interconnection Procedures and Agreements since Order 2003 was issued 15 years ago.  Order 845 adopts reforms that are designed to address three goals: (1) improving certainty for interconnection customers, (2) promoting more informed interconnection decisions, and (3) enhancing the interconnection process.

Order 845 revises FERC’s pro forma Large Generator Interconnection Procedures (“LGIP”) and Large Generator Interconnection Agreement (“LGIA”) to recognize the changing landscape of technology and is intended to provide interconnection customers with new opportunities to interconnect their projects faster and more cost-effectively.  For example, transmission providers must now allow interconnection customers (at the interconnection customer’s option) to build the needed transmission owner interconnection facilities and stand-alone network upgrades in all cases. Previously, interconnection customers only had this option if the transmission owner could not meet the dates proposed by the interconnection customer.  Thus, an interconnection customer has newly granted flexibility in the construction of the transmission owner interconnection facilities and stand-alone network upgrades. If the transmission owner returns a high cost estimate, then the interconnection customer can manage the construction of the transmission owner interconnection facilities. On the other hand, if the transmission owner cost estimate is reasonable, the interconnection customer can choose to leave the construction responsibilities for the transmission owner interconnection facilities and stand-alone network upgrade with the transmission owner. Interconnection customers can now make these decisions based on both timing and cost considerations.Continue Reading Helping the Hook-Up: FERC’s Generator Interconnection Procedures Reform Seeks to Improve Information Flow, Recognizes Changing Technology and Opens Further Opportunities for Storage

In February, FERC issued Order 841, Electric Storage Participation in Markets Operated by Regional Transmission Organizations and Independent System Operators (the “Order”), requiring RTOs and ISOs to establish new market participation rules for energy storage that recognize the physical and operational characteristics of these resources. While the Order set forth some minimal requirements that

On February 8, 2018, the California Public Utilities Commission (“CPUC”) adopted a new procurement process in a decision which suggested that 2,000 MW of new battery energy storage resources may be needed in California by 2030. This means an additional 2,000 MW of storage on top of the existing 1,325 MW that is already required.

The investment tax credit (“ITC”) plays a major role in driving investment in the U.S. solar energy market. Earlier this month, two members of Congress introduced a bill in the U.S. House of Representatives to provide a similar ITC for energy storage systems.

The bill, called the Energy Storage Tax Incentive and Deployment

On December 1, 2017, two of the three major California investor-owned utilities (“IOUs”), Pacific Gas & Electricity (“PG&E”) and Southern California Edison (“SCE”), submitted applications for approval of the results of their 2016-2017 energy storage request for offers.

Background on the Energy Storage Mandate in California

In September 2010,

By a notice issued yesterday, September 28, Rick Perry, the Secretary of Energy, utilized section 403 of the DOE Act to require FERC to cause organized energy market operators (ISOs/RTOs) to compensate “fuel secure generation”, i.e., coal power, for grid “resiliency”–something that apparently puts Americans at risk despite statements by NERC to the contrary or

Stoel Rives’ Energy Team has been monitoring and providing summaries of key energy-related bills introduced by California legislators since the beginning of the 2017-2018 Legislative Session. Legislators have been busy moving bills through the legislative process since reconvening from the Summer Recess. For any bill not identified as a two-year bill, the deadline for each house to pass the bill and present it to the Governor for signature or veto was September 15, 2017. Below is a summary and status of bills we have been following.

An enrolled bill is one that has been through the proof-reading process and is sent to the Governor to take action. A two-year bill is a bill taken out of consideration during the first year of a regular legislative session, with the intent of taking it up again during the second half of the session.

  • Of particular note here is SB 100, California’s pitch for 100 percent renewable energy, failed to move to the next stage of the process and is kicked to next year.
  • Our next blog post, after October 15, will provide an update on whether those bills sent to Governor Brown were signed or vetoed.

Continue Reading Updates to Energy Related Bills in the 2017-2018 California Legislative Session

Massachusetts recently became the latest state to adopt an energy storage target, following California’s lead, and recent storage legislation in Nevada and New York.

The Massachusetts storage mandate originated in the legislature last year, when the state legislature passed H.4568, which was signed by the Governor on August 8, 2016. The legislation required the state’s

On May 19, 2017, the California Public Utilities Commission (CPUC) and the California Energy Commission (CEC) held a joint en banc on customer and retail choice in California. In attendance were CPUC Commissioners Guzman Aceves, Randolph, Peterman, and President Picker.  CEC Commissioners McAllister, Douglas, and Chair Weisenmiller attended.

The en banc was intended to address

On April 6th, the energy storage market received a boost in California when state regulators authorized $196 million in new rebates for customers who install onsite (behind the meter) energy storage systems.

Background

The change occurs under the California Self Generation Incentive Program (“SGIP”). SGIP provides a financial rebate to energy customers who install new