As a follow up to our post here, the Minnesota Court of Appeals issued a decision on August 23 affirming the MPUC’s decisions related to the Nemadji Trail Energy Center natural gas plant (NTEC) that will be constructed in Superior, Wisconsin.  Applying a deferential standard of review, the Court analyzed the appeal (on remand

As a follow up to a previous post the Minnesota Supreme Court issued its decision on April 21, 2021, reversing the Minnesota Court of Appeals and remanding the matter for further review.  In so doing, the Court concluded that the Minnesota Public Utilities Commission properly concluded that MEPA review was not required.

The Court first

On December 23, 2019, the Minnesota Court of Appeals reversed and remanded a decision by the Minnesota Public Utilities Commission (the “Commission”) approving affiliated-interest agreements permitting Minnesota Power and its Wisconsin affiliate to move forward with the construction of a large natural gas facility – the Nemadji Trail Energy Center (“NTEC”) – in Superior, Wisconsin (the “Order”). The result of the Order may complicate the already complex issue of state permitting, specifically a state’s ability to regulate activity occurring in another state.

Honor the Earth and certain Clean Energy Organizations sought additional review of the Commission’s order based on concern about the lack of a Commission-ordered environmental assessment worksheet (“EAW”) pursuant to the Minnesota Environmental Policy Act (“MEPA”). During the initial Commission proceeding, Minnesota Power, and indeed the Commission, determined that an EAW was not necessary because (1) MEPA does not apply to the affiliated-interest agreements because NTEC does not meet the definition of “project” under MEPA, and (2) the Commission does not have authority to order an EAW for a project located in Wisconsin. In its Order, the Court of Appeals addresses each point, in turn.

The Order holds that MEPA applies to affiliated-interest agreements. Contrary to the Commission’s interpretation, the Court of Appeals concludes that the NTEC affiliated-interest agreements are “projects” as defined by MEPA. The Court’s definition of “project” is “a definite, site-specific, action that contemplates on-the-ground environmental changes.” The Order notes that the construction and operation of NTEC are definite and site-specific actions that will affect the immediate location as well as the surrounding environment (including Minnesota – 2.5 miles away – and Lake Superior). The Court went on to note that because the construction of NTEC is an environmentally significant event that may not occur without Commission approval of the affiliated-interest agreements, Commission approval of such agreements constitutes indirect governmental action manipulating the environment and triggering MEPA. Therefore, the Court concluded that MEPA “applies to the governmental action of approving the NTEC affiliated-interest agreements.”Continue Reading Minnesota Court of Appeals Determines MEPA Review Required for Wisconsin Natural Gas Generating Facility

On June 21, 2018, the United States District Court, District of Minnesota issued an order and memorandum rejecting a challenge to the constitutionality of Minn. Stat. § 216B.246 and granting defendants’ motions to dismiss. The statute, which was enacted after FERC Order 1000 (and eliminating the federal right of first refusal or “ROFR”), provides incumbent

On May 9, 2018 the Minnesota Public Utilities Commission issued an order approving Xcel Energy’s residential electric vehicle (“EV”) pilot program (the “Pilot”), designed as an alternative to Xcel’s existing EV tariff, concluding that the Pilot will “benefit all ratepayers by aiding Xcel in its efforts to integrate EV load as cost-effectively as possible.” A

Yesterday, Governor Mark Dayton announced his appointment of Minnesota State Senator Katie Sieben to a six-year term on the Minnesota Public Utilities Commission (MPUC). He also appointed current MPUC commissioner Nancy Lange as chair of the MPUC, filling the vacancy left by outgoing chair Beverly Jones Heydinger. Both Sieben and Lange will begin their terms

Minnesota Power released a Request for Proposals (RFP) yesterday for up to 300 MW of wind generation, with proposals due by September 7, 2016. A copy of the RFP and additional details are available at http://www.mnpower.com/Company/PowerSupplyRFP. Minnesota Power also filed its press release with the Minnesota Public Utilities Commission (MPUC).

Minnesota Power will also

The Minnesota Public Utilities Commission (MPUC) approved several major changes to Xcel Energy’s Community Solar Garden (CSG) program yesterday, while also voting to maintain other aspects of the CSG program. Mike Hughlett of the Star Tribune has this report. The MPUC’s decisions are summarized below:

Bill Credit Rate

  • Declined to modify the Applicable Retail

Today, the Eighth Circuit determined that the Next Generation Energy Act (“NGEA”), a Minnesota law that established power sector standards for carbon dioxide emissions, was unconstitutional (decision available here). In so doing, the Court affirmed the decision of District Court Judge Susan Nelson, whose 2014 decision we covered in “Court Declares Minnesota

The Minnesota Court of Appeals filed its decision today affirming the Public Utilities Commission’s August 6, 2015 Order in the community solar garden proceeding, which adopted the partial settlement agreement between certain solar developers and Xcel Energy and decided several crucial aspects of Xcel’s community solar program, including the 5 MW cap on co-located gardens.