The Minnesota Public Utilities Commission today issued its long-awaited Order approving (with modifications) Xcel Energy’s Community Solar Garden (CSG) Program – Solar Rewards*Community. The Order starts the clock for the program to open no later than 90 days from issuance of the Order (mid-December) and officially plows the furrow for community solar projects in Minnesota. It is not, however, clear that Xcel Energy will have the luxury of using the full 90 days for opening its CSG program- the Minnesota CSG Statute requires Xcel Energy to begin crediting subscriber accounts for each CSG within 180 days of the CSG plan’s approval. Stay tuned for additional details.
Our prior blogs provide more details on the program. We review the details of the Order below.
Application: Once applicants file their applications and deposits, Xcel has 30 days to confirm the application is complete and then another 60 days to accept or reject the application. Applicants initially need to include:
- Contact information,
- Garden information including system location and specifications,
- Application fee ($1,200) and deposit ($100/kW)
- Engineering documents, including one-line diagrams, site plan, and Interconnection Application
Applicants will have a full 24 months from Xcel’s completeness determination to complete the project and comply with several additional requirements including: proof of site control, adequate insurance, projection of subscriptions, and signed interconnection and CSG agreements.
Continue Reading Minnesota Community Solar Garden Program Approved, Set to Open