On September 24, 2021, the Federal Energy Regulatory Commission issued an order (176 FERC ¶ 61,207) approving tariff revisions to amend the California ISO’s (CAISO) interconnection procedures for its current queue cluster (Cluster 14).  The CAISO had requested changes to its interconnection procedures due to the massive increase in the number of interconnection requests it received this year—373 interconnection requests representing 150,000 megawatts of generating capacity, as compared to the 155 requests in 2020.  Prior to 2021, the average number of interconnection requests that the CAISO received each year over the past 10 years was 113.  The volume of interconnection requests in 2020 caused the CAISO to issue a market notice to delay the publication of Phase I interconnection study results by one month, pursuant to its tariff authority to extend the timing for providing study results under Sections 6.6 and 8.5 of its Generator Interconnection and Deliverability Allocation Procedures (GIDAP, Tariff Appendix DD).

Rather than rely on these tariff provisions to extend the study timelines for Cluster 14, however, the CAISO sought approval to establish extensions for various interconnection deadlines early in the process, to provide generators with advance notice of the timing for Cluster 14.  Per the approved tariff revisions, Cluster 14 deadlines will be extended as follows:
Continue Reading FERC Approves Changes to CAISO Interconnection Procedures; Next Queue Cluster Application Window Not Scheduled to Open Until 2023

In the wake of Governor Newsom’s July 30, 2021 Emergency Proclamation intended to mitigate the strain on the California energy grid, the California Department of Water Resources (CDWR) and the California Energy Commission have been reaching out to generation owners that could accommodate the addition of 30 MW gas turbines generators, an effort now referred to as the State Power Augmentation Project.  So far, two sites have been found:  Greenleaf 1 in Yuba City and Roseville Energy Park.  Each site will accommodate two turbines.  The units were supposed to come online in mid-September.

The two turbines at Roseville Energy Park will be interconnected through the Balancing Authority of Northern California and will participate in the California ISO’s (CAISO) energy imbalance market.  The two turbines at Greenleaf 1 will interconnect to the CAISO.  Under current tariff provisions, the CAISO can interconnect 50 MWs of the 60 MW total.  The Greenleaf 1 site has cogeneration facilities that are currently mothballed but still retain existing interconnection capacity of 49.2 MWs.  Because both the cogeneration facilities and the new gas turbines are gas-fired, there will be no change to the electrical characteristics, and the CAISO can therefore interconnect the two turbines under the repowering provisions of the tariff, but only up to 49.2 MWs.
Continue Reading FERC Grants Limited Waiver to the CAISO to Immediately Interconnect Gas Turbines

In June 2021, the California Public Utilities Commission (Commission) issued its Mid-Term Reliability Procurement Decision, Decision (D.) 21-06-035, which directed load-serving entities subject to its jurisdiction (investor-owned utilities, community choice aggregators, and energy service providers) to procure at least 11,500 megawatts (MW) of net-qualifying capacity (NQC) for reliability for the period 2023 through 2026.  The decision established cumulative annual procurement requirements: 2,000 MW in 2023, 6,000 MW in 2024, 1,500 MW in 2025, and 2,000 in 2026.  The decision also states that the Commission expects all of the resources procured pursuant to that decision to be zero-emitting, unless they otherwise qualify under renewables portfolio standard eligibility requirements (biomass, for example).
Continue Reading CPUC Issues Net-Qualifying Capacity Values to Be Used for Mid-Term Reliability Procurement

As a follow up to our post here, the Minnesota Court of Appeals issued a decision on August 23 affirming the MPUC’s decisions related to the Nemadji Trail Energy Center natural gas plant (NTEC) that will be constructed in Superior, Wisconsin.  Applying a deferential standard of review, the Court analyzed the appeal (on remand

As a follow up to a previous post the Minnesota Supreme Court issued its decision on April 21, 2021, reversing the Minnesota Court of Appeals and remanding the matter for further review.  In so doing, the Court concluded that the Minnesota Public Utilities Commission properly concluded that MEPA review was not required.

The Court first

Today was a big day for the solar power industry at the Federal Energy Regulatory Commission (FERC).

In its monthly open meeting, FERC announced two decisions that significantly impact the industry — one involving PURPA and the other related to PJM’s Minimum Offer Price Rule (MOPR).

First, FERC reversed its Broadview Solar decision issued in

On August 19, the California Public Utilities Commission (CPUC) issued a proposed decision accepting the 2019 Renewables Portfolio Standard Procurement Plans submitted by four new Community Choice Aggregators (CCAs): Butte Choice Energy Authority; Clean Energy Alliance; the City of Santa Barbara; and San Diego Community Power.  Each of these CCAs is anticipated to start providing

On July 17, 2020, the U.S. District Court for the Eastern District of California rendered its decision in U.S. v. California (Case 2:19-cv-02142-WBS-EFB), upholding the agreement between California and the Canadian Province of Québec that links California and Québec’s respective cap-and-trade programs.  In its opinion, the District Court rejected the federal government’s claim that the California-Québec agreement is preempted under the Foreign Affairs Doctrine.  The District Court ruled earlier this year on the federal government’s other claims, finding that the agreement did not violate either the Treaty or Compact Clauses of the U.S. Constitution.  With the decision on July 17, the California-Québec agreement will remain in place, allowing the two jurisdictions to continue to link their cap-and-trade programs.  The federal government has not yet stated whether it will appeal the District Court’s decision.
Continue Reading U.S. District Court Upholds California’s Cap-and-Trade Agreement with Québec

Yesterday, the Federal Energy Regulatory Commission (FERC) issued Order No. 872 and implemented the largest overhaul to FERC’s regulations affecting Qualifying Facilities (QFs) in more than a decade.  The order itself is 491 pages in length and there remain plenty of details to unpack in its implementation (including future proceedings to come at the FERC

On Friday, July 10, 2020, the U.S. Court of Appeals for the D.C. Circuit (“D.C. Circuit”) upheld the Federal Energy Regulatory Commission’s (“FERC”) Order Nos. 841 and 841A, which established a framework for electric storage resources’ (“ESRs”) participation in wholesale markets. The D.C. Circuit rejected the petitioners’ arguments that FERC exceeded its jurisdictional boundaries and