The Oregon Department of Energy (ODOE) is kicking off the stakeholder engagement part of its Floating Offshore Wind Study on January 20 at 9 a.m. As directed by HB 3375, ODOE is preparing a report on the challenges and benefits of integrating up to 3 gigawatts (GW) of floating offshore energy into Oregon’s grid by 2030, and it will submit that report to the legislature in September. A summary from the first part of the study, a literature review, should be released soon. Following the kickoff meeting, ODOE anticipates two more virtual meetings, as well as an opportunity to submit comments.
Continue Reading Oregon Department of Energy Seeks Stakeholder Input on Floating Offshore Wind Development

On November 18, 2021, FERC issued a Notice of Inquiry (NOI) seeking comments on reactive power capability compensation and market design.  (Link to NOI here). Reactive power is a critical component of the bulk electric system. Almost all bulk electric power is generated, transported, and consumed in AC networks. These AC systems consume both real and reactive power. Reactive power supports the voltages necessary for system reliability to allow the supply of real power from generation to load. All balancing authorities must procure enough sources of reactive power to safely manage the grid and generator interconnection agreements contain provisions requiring generators to operate within certain reactive power limits. Reactive power is an ancillary service and costs are recovered separately from the cost of standard transmission service.
Continue Reading Reactive Power Compensation for Renewable Generators – On the Chopping Block?

In June 2021, the California Public Utilities Commission (Commission) issued its Mid-Term Reliability Procurement Decision, Decision (D.) 21-06-035, which directed load-serving entities subject to its jurisdiction (investor-owned utilities, community choice aggregators, and energy service providers) to procure at least 11,500 megawatts (MW) of net-qualifying capacity (NQC) for reliability for the period 2023 through 2026.  The decision established cumulative annual procurement requirements: 2,000 MW in 2023, 6,000 MW in 2024, 1,500 MW in 2025, and 2,000 in 2026.  The decision also states that the Commission expects all of the resources procured pursuant to that decision to be zero-emitting, unless they otherwise qualify under renewables portfolio standard eligibility requirements (biomass, for example).
Continue Reading CPUC Issues Net-Qualifying Capacity Values to Be Used for Mid-Term Reliability Procurement

In docket R.20-05-003, its Integrated Resource Planning (IRP) proceeding, the California Public Utilities Commission is considering its preferred portfolio of new resources for the next ten years.  A lengthy administrative law judge ruling issued August 17, 2021 set out a suggested Preferred System Plan (PSP) for the proceeding, including a suggested resource portfolio through 2032,

This post was co-authored by Stoel Rives summer associate Lydia Heye.

In May, the U.S. Fish and Wildlife Service (“Service”) announced a proposed rule revoking the Trump administration’s final rule on incidental take under the Migratory Bird Treaty Act (“MBTA”). In the January 7, 2021 final regulation, the Trump administration interpreted the MBTA’s take prohibition

On August 19, the California Public Utilities Commission (CPUC) issued a proposed decision accepting the 2019 Renewables Portfolio Standard Procurement Plans submitted by four new Community Choice Aggregators (CCAs): Butte Choice Energy Authority; Clean Energy Alliance; the City of Santa Barbara; and San Diego Community Power.  Each of these CCAs is anticipated to start providing