The Federal Energy Regulatory Commission’s (“FERC”) long-awaited Order 845 (Reform of Generator Interconnection Procedures and Agreements) was issued on April 19 after over two years of consideration of the issues. Order 845 is the first grid-wide major reform of FERC’s Generator Interconnection Procedures and Agreements since Order 2003 was issued 15 years ago. Order 845 adopts reforms that are designed to address three goals: (1) improving certainty for interconnection customers, (2) promoting more informed interconnection decisions, and (3) enhancing the interconnection process.
Order 845 revises FERC’s pro forma Large Generator Interconnection Procedures (“LGIP”) and Large Generator Interconnection Agreement (“LGIA”) to recognize the changing landscape of technology and is intended to provide interconnection customers with new opportunities to interconnect their projects faster and more cost-effectively. For example, transmission providers must now allow interconnection customers (at the interconnection customer’s option) to build the needed transmission owner interconnection facilities and stand-alone network upgrades in all cases. Previously, interconnection customers only had this option if the transmission owner could not meet the dates proposed by the interconnection customer. Thus, an interconnection customer has newly granted flexibility in the construction of the transmission owner interconnection facilities and stand-alone network upgrades. If the transmission owner returns a high cost estimate, then the interconnection customer can manage the construction of the transmission owner interconnection facilities. On the other hand, if the transmission owner cost estimate is reasonable, the interconnection customer can choose to leave the construction responsibilities for the transmission owner interconnection facilities and stand-alone network upgrade with the transmission owner. Interconnection customers can now make these decisions based on both timing and cost considerations.Continue Reading Helping the Hook-Up: FERC’s Generator Interconnection Procedures Reform Seeks to Improve Information Flow, Recognizes Changing Technology and Opens Further Opportunities for Storage