On November 18, 2021, FERC issued a Notice of Inquiry (NOI) seeking comments on reactive power capability compensation and market design.  (Link to NOI here). Reactive power is a critical component of the bulk electric system. Almost all bulk electric power is generated, transported, and consumed in AC networks. These AC systems consume both real and reactive power. Reactive power supports the voltages necessary for system reliability to allow the supply of real power from generation to load. All balancing authorities must procure enough sources of reactive power to safely manage the grid and generator interconnection agreements contain provisions requiring generators to operate within certain reactive power limits. Reactive power is an ancillary service and costs are recovered separately from the cost of standard transmission service.
Continue Reading Reactive Power Compensation for Renewable Generators – On the Chopping Block?

On September 24, 2021, the Federal Energy Regulatory Commission issued an order (176 FERC ¶ 61,207) approving tariff revisions to amend the California ISO’s (CAISO) interconnection procedures for its current queue cluster (Cluster 14).  The CAISO had requested changes to its interconnection procedures due to the massive increase in the number of interconnection requests it received this year—373 interconnection requests representing 150,000 megawatts of generating capacity, as compared to the 155 requests in 2020.  Prior to 2021, the average number of interconnection requests that the CAISO received each year over the past 10 years was 113.  The volume of interconnection requests in 2020 caused the CAISO to issue a market notice to delay the publication of Phase I interconnection study results by one month, pursuant to its tariff authority to extend the timing for providing study results under Sections 6.6 and 8.5 of its Generator Interconnection and Deliverability Allocation Procedures (GIDAP, Tariff Appendix DD).

Rather than rely on these tariff provisions to extend the study timelines for Cluster 14, however, the CAISO sought approval to establish extensions for various interconnection deadlines early in the process, to provide generators with advance notice of the timing for Cluster 14.  Per the approved tariff revisions, Cluster 14 deadlines will be extended as follows:
Continue Reading FERC Approves Changes to CAISO Interconnection Procedures; Next Queue Cluster Application Window Not Scheduled to Open Until 2023

In the wake of Governor Newsom’s July 30, 2021 Emergency Proclamation intended to mitigate the strain on the California energy grid, the California Department of Water Resources (CDWR) and the California Energy Commission have been reaching out to generation owners that could accommodate the addition of 30 MW gas turbines generators, an effort now referred to as the State Power Augmentation Project.  So far, two sites have been found:  Greenleaf 1 in Yuba City and Roseville Energy Park.  Each site will accommodate two turbines.  The units were supposed to come online in mid-September.

The two turbines at Roseville Energy Park will be interconnected through the Balancing Authority of Northern California and will participate in the California ISO’s (CAISO) energy imbalance market.  The two turbines at Greenleaf 1 will interconnect to the CAISO.  Under current tariff provisions, the CAISO can interconnect 50 MWs of the 60 MW total.  The Greenleaf 1 site has cogeneration facilities that are currently mothballed but still retain existing interconnection capacity of 49.2 MWs.  Because both the cogeneration facilities and the new gas turbines are gas-fired, there will be no change to the electrical characteristics, and the CAISO can therefore interconnect the two turbines under the repowering provisions of the tariff, but only up to 49.2 MWs.
Continue Reading FERC Grants Limited Waiver to the CAISO to Immediately Interconnect Gas Turbines

Today was a big day for the solar power industry at the Federal Energy Regulatory Commission (FERC).

In its monthly open meeting, FERC announced two decisions that significantly impact the industry — one involving PURPA and the other related to PJM’s Minimum Offer Price Rule (MOPR).

First, FERC reversed its Broadview Solar decision issued in

In February 2018, as part of its efforts to remove barriers for electric storage resources, the Federal Energy Regulatory Commission (FERC) issued its final rule on electric storage participation in organized markets (Order No. 841).  Order No. 841 directed Regional Transmission Organizations (RTOs) and Independent System Operators (ISOs) to revise their tariffs to establish a

The Federal Energy Regulatory Commission (“FERC” or the “Commission”) issued two orders on July 18, 2019 revising the requirements applicable to market-based rate (“MBR”) sellers.  The first, Order No. 861, lightens the regulatory requirements for MBR sellers in certain RTO/ISO-administered markets by eliminating the requirement to submit indicative screens in the horizontal market power analysis in initial MBR applications, triennial updates, and change-in-status notices.  The second, Order No. 860, may also lighten regulation by reducing the amount of ownership information MBR sellers must report to the Commission, but also imposes new reporting requirements, including submissions to a relational database that will be maintained by FERC Staff to link MBR sellers and their affiliates.

Order No. 861

Order No. 861 eliminates the requirement that MBR sellers in RTO/ISO-administered energy, ancillary services, and capacity markets subject to FERC-approved RTO/ISO market monitoring and mitigation submit indicative horizontal market power screens.  Instead, a seller may include a statement in its filing that it is relying on FERC-approved market monitoring and mitigation to mitigate any potential market power.  With the exception of MBR sellers making capacity sales in CAISO and SPP, discussed below, this will lighten regulation on MBR sellers in ISOs/RTOs by eliminating the requirement to submit indicative screens in their initial MBR applications, triennial updates, and change-in-status notices.

The exemption will not apply to MBR sellers making capacity sales in CAISO or SPP, because CAISO and SPP do not have an RTO/ISO-administered capacity market.  In addition, the Commission determined that MBR capacity sellers in CAISO and SPP can no longer rely on the rebuttable presumption that FERC-approved RTO/ISO market monitoring and mitigation is sufficient to address horizontal market power concerns for their capacity sales in CAISO and SPP.  Therefore, SPP and CAISO capacity sellers must still submit indicative screens and, now, any seller that fails the indicative screens must submit a delivered price test or other evidence that it lacks market power in the capacity markets.  CAISO and SPP sellers will be able to rely on Order No. 861’s exemption for their sales of energy and ancillary services.

The order is effective September 24, 2019 and FERC Staff announced that the new rules will be applicable to triennial reviews for the Northeast region due in December 2019 and June 2020.Continue Reading FERC Issues Orders Revising Requirements for Market-Based Rate Sellers

In a move that was widely anticipated across the energy industry, the Federal Energy Regulatory Commission (FERC) today issued an order that terminated a notice of proposed rulemaking that had been initiated in October 2017 in response to a demand by Energy Secretary Rick Perry that FERC enact rules to compensate certain resources for what

Or so Secretary Rick Perry and the DOE would have us believe.  Approximately three weeks ago, the DOE made its pitch to FERC and the energy industry that a lack of “resiliency” threatens the U.S. power grid.  The responses are in.  And the shock and bewilderment that immediately followed the release of the Secretary’s surprising

Tax equity investments, and potentially other passive investments, in renewable energy just became that much easier to make.  Today, in response to a petition for declaratory order filed in January 2017 by a coalition of investors and project sponsors, FERC ruled that tax equity investments in public utilities does not trigger section 203 of the

By a notice issued yesterday, September 28, Rick Perry, the Secretary of Energy, utilized section 403 of the DOE Act to require FERC to cause organized energy market operators (ISOs/RTOs) to compensate “fuel secure generation”, i.e., coal power, for grid “resiliency”–something that apparently puts Americans at risk despite statements by NERC to the contrary or