In February 2018, as part of its efforts to remove barriers for electric storage resources, the Federal Energy Regulatory Commission (FERC) issued its final rule on electric storage participation in organized markets (Order No. 841). Order No. 841 directed Regional Transmission Organizations (RTOs) and Independent System Operators (ISOs) to revise their tariffs to establish a … Continue Reading
At its March 14, 2019 voting meeting, the California Public Utilities Commission (“CPUC”) voted out an Order Instituting Rulemaking (“OIR”) to Implement Senate Bill 237 (“SB 237”) Regarding Direct Access and to Consider Changes to Existing Direct Access Procedures. The Rulemaking will address the expansion of Direct Access, as required by SB 237. Direct Access … Continue Reading
On June 21, 2018, the United States District Court, District of Minnesota issued an order and memorandum rejecting a challenge to the constitutionality of Minn. Stat. § 216B.246 and granting defendants’ motions to dismiss. The statute, which was enacted after FERC Order 1000 (and eliminating the federal right of first refusal or “ROFR”), provides incumbent … Continue Reading
In a move that was widely anticipated across the energy industry, the Federal Energy Regulatory Commission (FERC) today issued an order that terminated a notice of proposed rulemaking that had been initiated in October 2017 in response to a demand by Energy Secretary Rick Perry that FERC enact rules to compensate certain resources for what … Continue Reading
Stoel Rives’ Energy Team has been monitoring and providing summaries of key energy-related bills introduced by California legislators since the beginning of the 2017-2018 Legislative Session. June 2, 2017 was the deadline by which the legislature was required to pass bills out of the house of origin. Failing to meet that deadline does not automatically … Continue Reading
On April 4, 2017 (NextEra Desert Center Blythe, LLC v. FERC, Case No. 16-1003 (“NextEra”)), the DC Circuit issued a decision remanding back to the Federal Energy Regulatory Commission (“FERC”) orders denying NextEra Desert Center Blythe, LLC’s (“NextEra”) complaint against the California Independent System Operator Corporation (“CAISO”) regarding the allocation of congestion revenue rights (“CRRs”) … Continue Reading
Yesterday, the Minnesota Department of Commerce issued its highly anticipated Minnesota Renewable Energy Integration and Transmission Study, which indicated that the “capacity for adding additional wind and solar up to 40% by 2030 can be reliably accommodated by the electric power system” (DOC press release here). The study stated that with relatively modest upgrades to existing transmission, … Continue Reading
FERC issues a proposed rulemaking that impacts the owners of gen-tie lines, and the rulemaking is particularly important to renewable energy developers who are interested in maintaining priority to gen-tie capacity for multi-phase projects.… Continue Reading
The East Kern Wind Resource Area (EKWRA)–it’s a mouthful–and it’s also a hotbed for renewable energy development and the location of a fight over millions of dollars among Southern California Edison (SCE), the California ISO, and independent power developers (IPPs). Late last week, the Federal Energy Regulatory Commission (FERC) scored that fight in favor of … Continue Reading
Ameren is dusting off a discriminatory method for interconnection customers to fund network upgrades in the Midcontinent ISO region, using two past victories in support of its campaign. But there are key differences between this dispute and those before it, and FERC should deny Ameren's latest attempt to breathe life into the Option 1 funding that met its fate years ago.… Continue Reading
Like other Independent System Operators have done before it, the Southwest Power Pool (SPP) is back at the drawing board in an effort to further refine its generator interconnection procedures and improve on queue reforms initially put in place in 2009. And also like other ISOs that have continued to tinker with queue reform, SPP … Continue Reading
Interconnection customers: be on notice. Your interconnection agreement may not be just a transmission provider service agreement that allows your project to interconnect with the transmission system. It may also be a rate schedule–your rate schedule–that you must file with FERC or suffer the consequences for violating the Federal Power Act. At last … Continue Reading
From my colleague, Andrew Moratzka: On June 7th, 2013, the United States Court of Appeals for the Seventh Circuit issued an opinion in Illinois Commerce Commission, et al., v. Federal Energy Regulatory Commission, affirming the Federal Energy Regulatory Commission’s approval of the Midcontinent Independent System Operator, Inc. (MISO) Multi-Value Project (MVP) tariff for financing new … Continue Reading
On Friday, March 30, 2012, the Federal Energy Regulatory Commission (the “Commission”) conditionally approved a proposal from the Midwest Independent System Operator (“MISO”) to change its generator interconnection queue procedures to address backlogs and late-state terminations of generation interconnection queue agreements (FERC Docket No. ER12-309-000). The new procedures are effective January 1, 2012. The reforms … Continue Reading
The Bonneville Power Administration (BPA) is gearing up for spring with its revised Oversupply Management Protocol (OMP), submitted last week as a compliance filing in the Federal Energy Regulatory Commission (FERC) proceeding on BPA’s “Environmental Redispatch” policy. BPA’s compliance filing was submitted in response to FERC’s December 7, 2011 order holding that BPA’s Environmental Redispatch policy … Continue Reading
The Bonneville Power Administration (“BPA”) made headlines this week with the release of its Draft Oversupply Management Protocol (the “Draft Oversupply Protocol”). BPA’s Draft Oversupply Protocol is intended to address concerns raised by BPA’s Environmental Redispatch (“ER”) policy of curtailing wind generation without compensation during periods of high water. Back in December, in response to a complaint … Continue Reading
The CUB Policy Center, in partnership with the University of Oregon School of Law, will be holding its inaugural policy conference: Smart Grid: Today’s Regulation and Tomorrow’s Technology, on Friday, October 21, 2011, at the University of Oregon White Stag Block (70 NW Couch St., Portland, OR 97209). The luncheon keynote speaker will be former FERC Commissioner … Continue Reading
Puget Sound Energy (PSE) has filed with the Washington Utilities and Transportation Commission (WUTC) a Request for Proposals for All Generation Sources (the all-source RFP) and a Request for Proposals for Electric and Demand Side Resources (energy-efficiency RFP). PSE filed the draft all source RFP on August 1, 2011 and plans to issue a separate … Continue Reading
Yesterday, the Federal Energy Regulatory Commission ("FERC" or "the Commission") issued Order No. 1000 in Docket No. RM10-23-000, a rulemaking proceeding initiated by the Commission on June 17, 2010. Order No. 1000 is a Final Rule that weighs in at a whopping 620 pages and reforms the Commission’s electric transmission planning and cost allocation requirements for public utility … Continue Reading
Stoel Rives Partners Alan Merkle, Ed Einowski and Michael Mangelson will participate in the upcoming Workshop on Investment in U.S. Wind Energy by Chinese Companies, held in Beijing, China on June 30, 2011. The opportunities for mutually beneficial cooperation between U.S. and China wind power industries have become increasingly profitable. Now more than ever it’s … Continue Reading
On Tuesday, June 28, 2011, the CPUC will hold an “Electric Energy Storage Workshop” as part of its R10-12-007 proceeding for AB 2514, which defines the process by which the CPUC will consider electric energy storage standards for California’s investor owned utilities. The workshop will be held at in the Golden Gate Room at CPUC’s … Continue Reading
On June 16, 2011, the Federal Energy Regulatory Commission (FERC) issued a Notice of Inquiry (NOI) seeking comments on what it described as two separate but related issues, both of which apply to electric energy storage (EES). First, because FERC is interested in facilitating the development of robust competitive markets to provide ancillary services from … Continue Reading
The Montana Supreme Court has reversed a December 2010 district court decision that found that the developers of the Montana-Alberta Tie Line merchant transmission project do not possess eminent domain authority under Montana law and therefore could not take private land from a nonconsenting landowner. In its reversal, the state Supreme Court cited House Bill … Continue Reading