On February 19, 2026, the Federal Energy Regulatory Commission (FERC) issued an order in Branch Street Solar Partners, LLC, addressing a rehearing and clarification request filed by several solar qualifying facilities (QFs) whose owners had failed to timely recertify their facilities after changes in ownership. In relevant part, the QF owners argued that their
D.C. Circuit Affirms FERC’s Definition of “Power Production Capacity” in Broadview Solar
December 9, 2025 Update: Following the D.C. Circuit’s September ruling, parties opted not to seek panel rehearing or en banc review. The deadline to petition the U.S. Supreme Court for certiorari expired on December 8, 2025, without any petitions for cert filed, thereby ending the potential for appeals of the decision.
———–
On September 9…
PJM Files Reliability Resource Initiative at FERC Requesting Expansion of Transition Cycle #2 for Reliability Resources
Overview
On December 13, 2024, PJM Interconnection, L.L.C. (“PJM”), filed with the Federal Energy Regulatory Commission (“Commission”) a modification to Part VII of its Open Access Transmission Tariff (“Tariff”), adding provisions to enable a one-time reliability-based expansion of the eligibility criteria for Transition Cycle #2 to allow a limited number of additional resources to enter…
FERC Issues Order Expanding Findings Related to Non-Independent Directors and Affiliation
On September 6, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued an order finding that the presence of a non-independent director, i.e., one who is affiliated with an investor, on the board of directors of a public utility or its upstream holding company creates an affiliation between the sponsor and the investor…
CAISO Interconnection Process Enhancements Proposal Faces Protest at FERC
CAISO’s Interconnection Process Enhancements proposal faces protests from independent power producers, clean energy organizations, and renewable energy developers at FERC. Challengers claim that CAISO’s scoring criteria provide undue influence to load-serving entities (LSEs) and may violate principles of open access.
CAISO’s proposal addresses the backlog in its interconnection queue by prioritizing projects in zones with…
Federal Energy Regulatory Commission Issues Long-Awaited Transmission Planning and Cost Allocation Final Rule
On May 13, 2024, at a special transmission reform meeting, the Federal Energy Regulatory Commission (FERC or Commission) issued Order No. 1920 “Building for the Future Through Electric Regional Transmission Planning and Cost Allocation” (Final Rule).[1] The Final Rule builds upon Order No. 888, Order No. 890, and Order No. 1000, which developed…
CAISO Releases Interconnection Process Enhancements Final Proposal
Summary
On March 29, 2024, the California Independent System Operator (CAISO) released the Track 2 final proposal for its Interconnection Process Enhancements (IPE) initiative. The proposed changes in the IPE proposal aim to address the “unprecedented and unsustainable interconnection request volumes” in the CAISO. CAISO proposes to adopt a zonal approach that prioritizes project interconnection in areas with existing or planned transmission capacity, to cap the number of projects permitted to proceed into the study process at 150% of the available and planned transmission capacity in specific zones, and adopt scoring criteria for eligibility and prioritization in the interconnection study process. Continue Reading CAISO Releases Interconnection Process Enhancements Final Proposal
FERC issues Final Rule on Improvements to Generator Interconnection Procedures and Agreements
At the July 27, 2023, Open Meeting, the Federal Energy Regulatory Commission (FERC) issued long-awaited Order No. 2023, the Final Rule on Improvements to Generator Interconnection Procedures and Agreements in Docket No. RM22-14-000. The rulemaking arose from the Advanced Notice of Proposed Rulemaking: Building for the Future Through Electric Regional Transmission Planning and Cost…
D.C. Circuit Affirms FERC’s Broadview Order Confirming that Qualifying Facilities May Install Greater than 80 MW of Nameplate Generating Capacity
7/8/2024 Update: The U.S. Supreme Court has vacated the D.C. Circuit’s order, discussed below. The D.C. Circuit applied Chevron deference in affirming FERC’s decision in the proceeding below. As a result, the U.S. Supreme Court has vacated and remanded back to the D.C. Circuit to reconsider the case in light of Chevron being overturned.
———–…
FERC Proposes Broad Reforms to Interconnection Process
At its June 16, 2022, open meeting, the Federal Energy Regulatory Commission (FERC or Commission) issued a notice of proposed rulemaking (NOPR), Improvements to Generator Interconnection Procedures and Agreements, 179 FERC ¶ 61,194 (2022), proposing reforms to the Commission’s standard generator interconnection procedures and agreements. The goal of the NOPR is to reduce queue…