On May 18, 2022, the California Energy Commission met to discuss its draft report to evaluate and quantify the maximum feasible capacity of offshore wind to achieve reliability, ratepayer, employment, and decarbonization benefits and establish megawatt offshore wind planning goals for 2030 and 2045. The report is the first of three interim work products that California AB 525 directs CEC to prepare. By the end of this year, the CEC must complete and submit a preliminary assessment of economic benefits as they relate to seaport investments and workforce development needs, and complete and submit a permitting roadmap. The ultimate requirement of AB 525 is to require, by June 30, 2023, the CEC, in coordination with federal, state, and local agencies and a wide variety of stakeholders, to develop a strategic plan for offshore wind energy developments installed off the California coast in federal waters and submit it to the California Natural Resources Agency and the Legislature.Continue Reading California Energy Commission Discusses Draft Report on Offshore Wind
California
Commission Ruling Reopens the NEM 3.0 Record to Invite Comment on and Consider Limited Issues
In its first move since hitting “pause” on the California Public Utilities Commission’s (Commission) consideration of a controversial December 2021 proposed decision (Proposed Decision or PD) that would have overhauled the existing net energy metering (NEM) tariff for California’s solar customers, the presiding administrative law judge (ALJ) issued a ruling on May 9 to reopen the record and invite party comments on a limited scope of issues.
Background
The Commission adopted California’s existing solar tariff, known as NEM 2.0, on January 28, 2016 in Decision (D.) 16-01-044. Customers opting into this tariff pay a one-time interconnection fee (less than $150 for systems under 1 MW and $800 for systems over 1 MW). Customers taking service on the NEM tariff are automatically opted into a time-of-use rate plan and are subject to select non-bypassable charges (NBCs) that are used to fund general customer programs such as contributions to the wildfire fund, nuclear decommissioning, and the public purpose program, among others. NEM customers receive a bill credit for any excess generation produced by their system and exported to the electric grid, which credits may be used to offset customer energy costs. Under NEM 2.0, any excess generation credits are applied to the customer’s bill at the same retail rate (including generation, distribution and transmission charges) the customer would have paid for the energy consumption.
Continue Reading Commission Ruling Reopens the NEM 3.0 Record to Invite Comment on and Consider Limited Issues
California Makes Progress Towards Ensuring Electric Reliability for Summer 2022
On January 11, 2022, the California Energy Commission (CEC) issued an update to its Summer 2022 Stack Analysis. Previously, on September 8, 2021, the CEC issued a revised Summer 2022 Stack Analysis that showed potential energy shortfalls ranging from 200 MW to 4,350 MW during the months of July through September 2022, in the evening…
California ISO Issues Straw Proposal in Interconnection Process Enhancements Stakeholder Proceeding
On December 6, 2021, the California ISO issued an issue paper and straw proposal (“Straw Proposal”) for its Interconnection Process Enhancements stakeholder proceeding. The California ISO initiated this stakeholder proceeding on September 30, 2021 with the issuance of a preliminary issue paper. The stakeholder process comes at a time when an unprecedented level of energy procurement in California has caused dramatic increases in the number of projects in the California ISO’s interconnection queue. The California ISO’s most recent cluster, cluster 14, saw a record number of 373 interconnection requests being submitted, representing 150,000 megawatts of generating capacity, compared to 155 requests submitted in 2020. Ultimately, the volume of interconnection requests forced the California ISO to seek authority from the Federal Energy Regulatory Commission to extend its interconnection process by approximately one year.
The Interconnection Process Enhancements initiative will have two phases. Phase 1 will focus on near-term enhancements for cluster 14 and before the summer of 2022. The proposals in Phase 1 are scheduled be submitted to the California ISO Board of Governors in May 2022. Phase 2 will focus on longer term modifications and broader reforms to align interconnection processes with procurement activities. Those proposals are scheduled to be submitted to the Board in November 2022.
Continue Reading California ISO Issues Straw Proposal in Interconnection Process Enhancements Stakeholder Proceeding
California Public Utilities Commission Takes Action to Prevent Outages During Summer 2022 and 2023
On October 29, 2021, the California Public Utilities Commission (CPUC) issued three proposed decisions intended to address potential electric capacity shortfalls in 2022 and 2023. The proposed decisions, if approved, would implement a variety of demand-side and supply-side policies designed to ensure that in the event of extreme weather during the summer of 2022 and/or 2023, California has sufficient electric capacity to avoid outages.
Background
In August 2020, the California ISO experienced outages during the evenings of August 14 and 15, and only extraordinary efforts, including voluntary conservation efforts by California energy users, allowed the California ISO to avoid outages the following week.
After those outages, the CPUC and the California Energy Commission (CEC) have been working towards addressing potential capacity shortfalls during extreme weather events during the summer. In November 2020, the CPUC opened a rulemaking (R.20-11-003) to ensure reliability in the event of extreme weather during the summer of 2021. In February 2021, the CPUC adopted a decision directing procurement of additional capacity (D.21-02-028), and in March, adopted a decision directing additional demand-side and supply-side actions to increase supply and decrease load during extreme weather events (D.21-03-056).
California managed to avoid outages during the summer of 2021, although it was helped by relatively mild weather in August and September. A stack analysis performed by the CEC this summer, however, showed the potential for capacity shortfalls of up to 4,350 megawatts (MW) for summer 2022. In August, the CPUC implemented a second phase to R.21-11-003, to ensure reliability during the summers of 2022 and 2023.
Continue Reading California Public Utilities Commission Takes Action to Prevent Outages During Summer 2022 and 2023
FERC Approves Changes to CAISO Interconnection Procedures; Next Queue Cluster Application Window Not Scheduled to Open Until 2023
On September 24, 2021, the Federal Energy Regulatory Commission issued an order (176 FERC ¶ 61,207) approving tariff revisions to amend the California ISO’s (CAISO) interconnection procedures for its current queue cluster (Cluster 14). The CAISO had requested changes to its interconnection procedures due to the massive increase in the number of interconnection requests it received this year—373 interconnection requests representing 150,000 megawatts of generating capacity, as compared to the 155 requests in 2020. Prior to 2021, the average number of interconnection requests that the CAISO received each year over the past 10 years was 113. The volume of interconnection requests in 2020 caused the CAISO to issue a market notice to delay the publication of Phase I interconnection study results by one month, pursuant to its tariff authority to extend the timing for providing study results under Sections 6.6 and 8.5 of its Generator Interconnection and Deliverability Allocation Procedures (GIDAP, Tariff Appendix DD).
Rather than rely on these tariff provisions to extend the study timelines for Cluster 14, however, the CAISO sought approval to establish extensions for various interconnection deadlines early in the process, to provide generators with advance notice of the timing for Cluster 14. Per the approved tariff revisions, Cluster 14 deadlines will be extended as follows:
Continue Reading FERC Approves Changes to CAISO Interconnection Procedures; Next Queue Cluster Application Window Not Scheduled to Open Until 2023
California ISO Survives the Summer with No Blackouts; Battery Energy Storage Beginning to Play Larger Role
The California ISO held its final Summer 2021 Readiness Update call on September 24. As reported on the call, the California ISO managed to get through summer 2021 without any load-shedding events, in contrast to last summer, when load-shedding events occurred on two days in August. The California ISO; California energy regulatory agencies, including the California Public Utilities Commission (CPUC) and California Energy Commission (CEC); and the Governor’s office have spent considerable effort to avoid any outages for both this summer and summer 2022. However, as California ISO Senior Vice President and Chief Operating Officer Mark Rothleder explained, California experienced less extreme weather this summer, which helped the state avoid outages. Although July was challenging, due to a West-wide heatwave and transmission impacted by the Bootleg Fire, August and September were more mild. In 2020, load peaked at 47,121 megawatts (MW) on August 18, at 15:57. In 2021, load peaked at 43,982 MW on September 8, at 17:50. By comparison, the California ISO’s highest peak was 50,270 MW in 2006.
Continue Reading California ISO Survives the Summer with No Blackouts; Battery Energy Storage Beginning to Play Larger Role
FERC Grants Limited Waiver to the CAISO to Immediately Interconnect Gas Turbines
In the wake of Governor Newsom’s July 30, 2021 Emergency Proclamation intended to mitigate the strain on the California energy grid, the California Department of Water Resources (CDWR) and the California Energy Commission have been reaching out to generation owners that could accommodate the addition of 30 MW gas turbines generators, an effort now referred to as the State Power Augmentation Project. So far, two sites have been found: Greenleaf 1 in Yuba City and Roseville Energy Park. Each site will accommodate two turbines. The units were supposed to come online in mid-September.
The two turbines at Roseville Energy Park will be interconnected through the Balancing Authority of Northern California and will participate in the California ISO’s (CAISO) energy imbalance market. The two turbines at Greenleaf 1 will interconnect to the CAISO. Under current tariff provisions, the CAISO can interconnect 50 MWs of the 60 MW total. The Greenleaf 1 site has cogeneration facilities that are currently mothballed but still retain existing interconnection capacity of 49.2 MWs. Because both the cogeneration facilities and the new gas turbines are gas-fired, there will be no change to the electrical characteristics, and the CAISO can therefore interconnect the two turbines under the repowering provisions of the tariff, but only up to 49.2 MWs.
Continue Reading FERC Grants Limited Waiver to the CAISO to Immediately Interconnect Gas Turbines
CPUC Issues Net-Qualifying Capacity Values to Be Used for Mid-Term Reliability Procurement
In June 2021, the California Public Utilities Commission (Commission) issued its Mid-Term Reliability Procurement Decision, Decision (D.) 21-06-035, which directed load-serving entities subject to its jurisdiction (investor-owned utilities, community choice aggregators, and energy service providers) to procure at least 11,500 megawatts (MW) of net-qualifying capacity (NQC) for reliability for the period 2023 through 2026. The decision established cumulative annual procurement requirements: 2,000 MW in 2023, 6,000 MW in 2024, 1,500 MW in 2025, and 2,000 in 2026. The decision also states that the Commission expects all of the resources procured pursuant to that decision to be zero-emitting, unless they otherwise qualify under renewables portfolio standard eligibility requirements (biomass, for example).
Continue Reading CPUC Issues Net-Qualifying Capacity Values to Be Used for Mid-Term Reliability Procurement
California Energy Commission Adopts Expedited Siting Order for Energy Storage
The California Energy Commission (CEC) has continued its efforts to implement Governor Newsom’s July 30, 2021 Emergency Proclamation, which was intended to free up energy supply to meet demand during extreme heat events and wildfires, and to expedite the deployment of additional generation.
The Emergency Proclamation authorized the CEC, which is responsible for licensing thermal powerplants of 50 megawatts (MW) or more, to also license new, or expansions of, battery storage systems of 20 MW or more that are capable of discharging for at least two hours and will deliver net peak energy by October 31, 2022.
Continue Reading California Energy Commission Adopts Expedited Siting Order for Energy Storage