On December 6, 2021, the California ISO issued an issue paper and straw proposal (“Straw Proposal”) for its Interconnection Process Enhancements stakeholder proceeding. The California ISO initiated this stakeholder proceeding on September 30, 2021 with the issuance of a preliminary issue paper. The stakeholder process comes at a time when an unprecedented level of energy … Continue Reading
On September 24, 2021, the Federal Energy Regulatory Commission issued an order (176 FERC ¶ 61,207) approving tariff revisions to amend the California ISO’s (CAISO) interconnection procedures for its current queue cluster (Cluster 14). The CAISO had requested changes to its interconnection procedures due to the massive increase in the number of interconnection requests it received … Continue Reading
In the wake of Governor Newsom’s July 30, 2021 Emergency Proclamation intended to mitigate the strain on the California energy grid, the California Department of Water Resources (CDWR) and the California Energy Commission have been reaching out to generation owners that could accommodate the addition of 30 MW gas turbines generators, an effort now referred … Continue Reading
FERC issues a proposed rulemaking that impacts the owners of gen-tie lines, and the rulemaking is particularly important to renewable energy developers who are interested in maintaining priority to gen-tie capacity for multi-phase projects.… Continue Reading
The East Kern Wind Resource Area (EKWRA)–it’s a mouthful–and it’s also a hotbed for renewable energy development and the location of a fight over millions of dollars among Southern California Edison (SCE), the California ISO, and independent power developers (IPPs). Late last week, the Federal Energy Regulatory Commission (FERC) scored that fight in favor of … Continue Reading
Ameren is dusting off a discriminatory method for interconnection customers to fund network upgrades in the Midcontinent ISO region, using two past victories in support of its campaign. But there are key differences between this dispute and those before it, and FERC should deny Ameren's latest attempt to breathe life into the Option 1 funding that met its fate years ago.… Continue Reading
Qualifying facility interconnection conversions can be an effective way to bypass the interconnection queue, even during a repower. But there are groundrules to a conversion, and today FERC applied those rules and determined that qualifying facility owners may not be entitled to as much converted capacity as they might think.… Continue Reading
Like other Independent System Operators have done before it, the Southwest Power Pool (SPP) is back at the drawing board in an effort to further refine its generator interconnection procedures and improve on queue reforms initially put in place in 2009. And also like other ISOs that have continued to tinker with queue reform, SPP … Continue Reading
Interconnection customers: be on notice. Your interconnection agreement may not be just a transmission provider service agreement that allows your project to interconnect with the transmission system. It may also be a rate schedule–your rate schedule–that you must file with FERC or suffer the consequences for violating the Federal Power Act. At last … Continue Reading
On Friday, March 30, 2012, the Federal Energy Regulatory Commission (the “Commission”) conditionally approved a proposal from the Midwest Independent System Operator (“MISO”) to change its generator interconnection queue procedures to address backlogs and late-state terminations of generation interconnection queue agreements (FERC Docket No. ER12-309-000). The new procedures are effective January 1, 2012. The reforms … Continue Reading
On January 31, 2012, the Federal Energy Regulatory Commission (FERC) conditionally accepted additional reforms to the California ISO’s Generator Interconnection Procedures (GIP) that significantly change the rules that apply to developers seeking to interconnect power generation facilities in the California ISO’s balancing authority area. The decision continues the California ISO’s efforts to reform the GIP … Continue Reading
A report from Stoel Rives attorney Jake Storms (Sacramento): The California Public Utility Commission (“CPUC”) recently announced that it will reopen the Rule 21 Working Group. Rule 21 governs the interconnection of distributed generation to a utility’s distribution system. Each of the three largest investor-owned utilities—Pacific Gas and Electric, Southern California Edison, and San Diego … Continue Reading