Tag: interconnection

The Price of Developing Power Projects in Kern County Just Went UP

The East Kern Wind Resource Area (EKWRA)–it’s a mouthful–and it’s also a hotbed for renewable energy development and the location of a fight over millions of dollars among Southern California Edison (SCE), the California ISO, and independent power developers (IPPs).  Late last week, the Federal Energy Regulatory Commission (FERC) scored that fight in favor of … Continue Reading

Ameren Should LOSE the Latest Battle Over Option 1 Network Upgrade Funding in the Midcontinent ISO Region

Ameren is dusting off a discriminatory method for interconnection customers to fund network upgrades in the Midcontinent ISO region, using two past victories in support of its campaign. But there are key differences between this dispute and those before it, and FERC should deny Ameren's latest attempt to breathe life into the Option 1 funding that met its fate years ago.… Continue Reading

Raising the Bar For Interconnection In the Southwest Power Pool

Like other Independent System Operators have done before it, the Southwest Power Pool (SPP) is back at the drawing board in an effort to further refine its generator interconnection procedures and improve on queue reforms initially put in place in 2009.  And also like other ISOs that have continued to tinker with queue reform, SPP … Continue Reading

Rate Schedules Galore! FERC’s Decision in Chehalis Power Generating, LP

Interconnection customers:  be on notice.  Your interconnection agreement may not be just a transmission provider service agreement that allows your project to interconnect with the transmission system.  It may also be a rate schedule–your rate schedule–that you must file with FERC or suffer the consequences for violating the Federal Power Act.     At last … Continue Reading

FERC Conditionally Approves MISO Queue Reform

On Friday, March 30, 2012, the Federal Energy Regulatory Commission (the “Commission”) conditionally approved a proposal from the Midwest Independent System Operator (“MISO”) to change its generator interconnection queue procedures to address backlogs and late-state terminations of generation interconnection queue agreements (FERC Docket No. ER12-309-000).  The new procedures are effective January 1, 2012.  The reforms … Continue Reading

The Interconnection Landscape Changes Yet Again: FERC Conditionally Accepts the California ISO’s Interconnection Queue Reform Phase 2

On January 31, 2012, the Federal Energy Regulatory Commission (FERC) conditionally accepted additional reforms to the California ISO’s Generator Interconnection Procedures (GIP) that significantly change the rules that apply to developers seeking to interconnect power generation facilities in the California ISO’s balancing authority area. The decision continues the California ISO’s efforts to reform the GIP … Continue Reading

California Public Utility Commission to Reopen Rule 21 Working Group

A report from Stoel Rives attorney Jake Storms (Sacramento): The California Public Utility Commission (“CPUC”) recently announced that it will reopen the Rule 21 Working Group. Rule 21 governs the interconnection of distributed generation to a utility’s distribution system. Each of the three largest investor-owned utilities—Pacific Gas and Electric, Southern California Edison, and San Diego … Continue Reading
LexBlog