On Thursday, May 9, 2024, the California Independent System Operator (CAISO) issued an addendum to its Interconnection Process Enhancements (IPE) Track 2 Final Proposal, and issued a revised version of that addendum on May 17.  Track 2 focuses on modifications to the interconnection and queue management processes to address the substantial interconnection request volumes in

Background

The California Independent System Operator’s (CAISO) recently issued Interconnection Process Enhancements (IPE) final proposal[1] provides heightened requirements to complete an interconnection request and relies on scoring criteria to determine which projects advance to the interconnection study process. Due to the proposed 150% cap on specific interconnection zones, not all interconnection requests in each

Summary

On March 29, 2024, the California Independent System Operator (CAISO) released the Track 2 final proposal for its Interconnection Process Enhancements (IPE) initiative. The proposed changes in the IPE proposal aim to address the “unprecedented and unsustainable interconnection request volumes” in the CAISO.  CAISO proposes to adopt a zonal approach that prioritizes project interconnection in areas with existing or planned transmission capacity, to cap the number of projects permitted to proceed into the study process at 150% of the available and planned transmission capacity in specific zones, and adopt scoring criteria for eligibility and prioritization in the interconnection study process. Continue Reading CAISO Releases Interconnection Process Enhancements Final Proposal