An update on Oklahoma from Laura Suesser and Sara Bergan:

The Oklahoma legislature passed three bills (H.B. 2973, S.B. 1787, and H.B. 3028) in 2010 that affect the renewable energy industry. Two have already gone into effect and the third will go into effect on January 1, 2011. A summary of each bill is included below.

The Oklahoma Wind Energy Development Act (the “Act”), H.B. 2973, becomes effective on January 1, 2011 and will be codified in Okla. Stat. tit. 17 §§160.11-17 (2010). The Act includes the following:

  • Decommissioning: Decommissioning requirements apply to any wind energy facility entering into or renewing a power purchase agreement (PPA) on or after January 1, 2011. If energy is not being sold under a PPA, the requirements apply to wind energy facilities which commence construction on or after January 1, 2011. The requirements include:
    • Restoration: Owners of a wind energy facility must remove wind energy equipment (to a depth of 30”) and restore land surfaces to substantially the same pre-construction condition (excluding roads) within 12 months of abandonment of a project or the end of the useful life of the equipment.
    • Cost Estimate and Posting of Financial Security: After the 15th year of operation, facility owners must file a professional estimate of the decommissioning costs together with a financial security (either a surety bond, collateral bond, parent guaranty or letter of credit) to cover such costs. Those failing to so file may incur an administrative penalty of up to $1,500/day.
  •  Payment Statements and Access to Records: Any owner or operator making payments to landowners based on the amount of electrical energy produced is required to deliver a statement to the landowner, within 10 business days of payment, explaining the payment calculation and a means for the landowner to confirm its accuracy. Landowners have the right to inspect owner/operator records to confirm the accuracy of payments for up to 24 months following payment. Records must be made available for review within the state of Oklahoma.  
  •  Insurance:   Owners or operators are required to obtain commercial general liability insurance policy with limits consistent with prevailing industry standards (or a combination of self insurance and excess liability insurance policy), which name the landowner as an additional insured and certificates of insurance must be delivered to landowner prior to commencing construction of the facility.

Continue Reading Oklahoma’s Significant Renewable Energy Legislation is Going Into Effect

On June 8, 2010, Utah Governor Gary Herbert launched a formal planning process for the Utah Energy Initiative.  Over the past several months the members of the Utah Energy Initiative Task Force and various subcommittees have conducted public hearings and a series of meetings to gather input for purposes of drafting a 10-year strategic energy plan.  The Energy Initiative Task Force issued a draft report on November 3, 2010.  Written comments on the draft report are due by November 10, 2010 and should be submitted to abuchholz@utah.gov.  A public hearing at which public comment will be accepted will be held on November 10, 2010 from 5:00 to 7:00 p.m., at the Senate Building (State Capitol complex east building), Room 215, Salt Lake City, Utah.

The energy plan outlined in the report contains the following themes:

  1. Economic Development and Energy Jobs
  2. Energy Development and Environment
  3. Energy Efficiency, Conservation and Demand-Response
  4. Transportation and Air Quality
  5. Transmission, Infrastructure and Transportation
  6. Developing and Applying Technology and Science

Continue Reading Utah Energy Initiative Task Force Issues Draft Plan

Sens. Jeff Bingaman (D-NM) and Sam Brownback (R-KS), with Sens. Byron Dorgan (D-ND), Susan Collins (R-ME), Tom Udall (D-NM), Mark Udall (D-CO) and others joining, announced today that they will introduce a stand-alone Renewable Electricity Standard (RES) bill.  The bill will require sellers of electricity to obtain the following milestones in adding renewable energy resources or energy efficiency:

2012-2013 – 3%

2014-2015 – 6%

2017-2018 – 9%

2019-2020 – 12%

2021 – 2039 -15%

Renewable resources that can be used toward compliance will include wind, solar, ocean, geothermal, biomass, landfill gas, incremental hydropower, hydrokinetic, new hydropower at existing dams, and waste-to-energy.  For utilities that are unable to meet their RES targets, the bill proposes to charge a compliance payment at a rate of 2.1 cents per kilowatt hour, with such amounts then being used for renewable energy development or to offset consumers’ bills.

A first step, yes.  But a small one.

Follow the link to learn more:Continue Reading A National Renewable Energy Standard Bill Surfaces in DC

I am proud to announce the publication of two white papers that focus on the issues of transmission development and broader issues facing renewable energy.  These white papers were written by attorneys at Stoel Rives and were prepared at the request of the Energy Foundation, a partnership of major foundations interested in sustainable energy.  The

On August 12, 2010, Energy Secretary Steven Chu announced a new loan guarantee solicitation for renewable energy manufacturing projects.  The Commercial Technology Renewable Energy Manufacturing Projects solicitation (the "Solicitation") is supported by the American Recovery and Reinvestment Act (the "Recovery Act") through Section 1705 of the Loan Guarantee Program and is focused primarily on providing new green energy jobs and the deployment of renewable energy technologies that reduce greenhouse gas emissions.

The solicitation specifically identified "Eligible Projects" to include renewable energy manufacturing projects or facilities located in the United States that:

  • Manufactures Commercial Technology products that support the generation of electricity or thermal energy from renewable resources;
  • Has Project Costs greater than seventy-five million dollars ($75,000,000);
  • Is able to obtain a credit rating equivalent of "BB" or better from Standard & Poor’s or Fitch, or "Ba2" or better from Moody’s, as evaluated without the benefit of any DOE guarantee or any other credit support;
  • Will create or retain jobs in the United States; and
  • Otherwise meets all applicable requirements of Title XVII, including Section 1705, the Solicitation, including all attachments and all applicable requirements of the Recovery Act.

The Solicitation also provided, for illustrative purposes, examples of the types of Eligible Projects that may qualify, which include the following:

  • wind energy component or systems manufacturing facilities;
  • solar photovoltaic (PV) component or system manufacturing facilities;
  • concentrated solar power component or system manufacturing facilities;
  • hydropower component or system manufacturing facilities;
  • geothermal component or system manufacturing facilities;
  • other geothermal power cycle component or system manufacturing facilities; or
  • ocean wave, tidal, and river current (e.g. hydrokinetic) component or system manufacturing facilities

Continue Reading Clean Energy Jobs Focus of New Manufacturing Solicitation Issued by the DOE

With a swift 13-page order today, FERC rejected Puget Sound Energy’s proposed wind integration rate, stating that the rate was not shown to be “just and reasonable” under section 205 of the Federal Power Act.  “Changing system conditions, such as an increasing amount of wind generation described by Puget, present unique challenges that may require

On June 30, 2010, the U.S. Department of Energy ("DOE") launched its Technology Commercialization Portal (the "Portal").  The Portal is an online resource that provides a mechanism for investors, entrepreneurs and companies to identify new technologies coming out of DOE laboratories and other participating research institutions.  Relevant technologies include:

  • Advanced Materials
  • Biomass and Biofuels
  • Building Energy Efficiency
  • Electricity Transmission and

The Nevada State Office of Energy (“NSOE”) announced on March 16, 2010, that is it has issued a Request for Proposals (“RFP”) for renewable energy projects under the $8M+ Revolving Loan Program. Projects must be no more than 60kW in size for solar PV and 20kW maximum for wind turbines and solar thermal. Loan terms

Federal tax benefits, such as the Section 1603 Grant, investment tax credits and production tax credits, continue to be an important driver in financing renewable energy projects.  Several of my colleagues will be discussing these tax benefits and other incentives related to project financing in a webinar hosted by Infocast on Wednesday, March 31, 2010 at 1:00